Job, Batch and Contract Costing Formulas

Job cost and pricing, economic batch quantity, retention money and profit recognition on contracts, with a worked contract example.

22 Job, Batch & Contract Costing formulas

Job, Batch & Contract Costing formulas (22)

FormulaExpression
Total Job CostJob Cost = Direct Material + Direct Labour + Direct Expenses + Absorbed OH
Job Price (Markup on Cost)Price = Job Cost × (1 + Markup %)
Batch Cost per UnitCost per Unit = Total Batch Cost/Units in Batch
Economic Batch Quantity (EBQ)EBQ = √(2DS/C), S = setup cost per batch, C = carrying cost per unit
Batch Setup Cost per UnitSetup Cost per Unit = Setup Cost per Batch/Batch Size
Total Cost of Batch RunBatch Cost = Setup Cost + (Variable Cost per Unit × Batch Size)
Job OverheadJob OH = OH Rate × Job Base Quantity
Job Cost VarianceJob Cost Variance = Budgeted Job Cost − Actual Job Cost
Abnormal Spoilage Cost (Job)Abnormal Spoilage Cost = Spoiled Units × Cost per Unit − Scrap Value
Contract Profit (Completed)Profit = Contract Price − Total Contract Cost
Retention MoneyRetention = Work Certified × Retention %
Cash Received on ContractCash Received = Work Certified − Retention Money
Estimated Contract ProfitEstimated Profit = Contract Price − (Cost to Date + Estimated Cost to Complete)
Profit Credited (Under 25% Complete)Profit Credited = Nil
Percentage of Completion (Cost Basis)% Complete = (Cost Incurred to Date/Total Estimated Cost) × 100
Revenue Recognised Over TimeRevenue to Date = Contract Price × % Complete
Amount Due from Customers (Contract)Amount Due = Cost Incurred + Recognised Profit − Progress Billings
Contract Escalation ClaimEscalation = Base Quantity × (Current Price − Base Price)
Plant Depreciation on ContractPlant Depreciation = (Cost − Residual Value)/Life × Period Used
Provision for Foreseeable Contract LossProvision = Total Expected Loss − Loss Already Recognised
Cost-Plus Fixed Fee ContractContract Price = Actual Cost + Fixed Fee
Incentive Contract FeeFee = Target Fee + Sharing % × (Target Cost − Actual Cost)

About these Job, Batch & Contract Costing formulas

Job and batch costing are used when work is done to order, or in groups of identical units. Contract costing is the same idea for large projects that run across more than one accounting period, so profit has to be recognised in stages.

The contract formulas follow the traditional rule taught in cost accounting courses: take no profit on a contract that is less than a quarter complete, take a fraction of the notional profit as it progresses, and use the estimated total profit when it is nearly finished. Confirm which rule your syllabus uses.

How to use these formulas

Worked example

Question. A contract has a price of Rs. 5,000,000. Work certified to date is Rs. 2,000,000, the retention is 10% and the cost of work to date is Rs. 1,700,000.

Retention = 2,000,000 × 10% = Rs. 200,000, so cash received = 2,000,000 − 200,000 = Rs. 1,800,000.

Stage of completion = 2,000,000 / 5,000,000 = 40%, which is between 25% and 50%.

Notional profit = work certified − cost of work to date = 2,000,000 − 1,700,000 = Rs. 300,000.

Profit credited = ⅓ × 300,000 × (1,800,000 / 2,000,000) = Rs. 90,000.

Common mistakes

FAQ

What is retention money in contract costing?

A percentage of each certified amount that the customer holds back until the contract is complete or defects are corrected. It reduces the cash received but not the work certified.

What is the difference between job costing and batch costing?

Job costing tracks the cost of one customer's order. Batch costing tracks the cost of a group of identical units made together and divides it by the batch size to get a cost per unit.

Why is only part of the profit taken on an incomplete contract?

Because of prudence: the final outcome is uncertain, so only a portion of the profit is recognised until the contract is far enough along for the estimate to be reliable.