Material Costing and Inventory Control Formulas

EOQ, reorder level, stock levels, ABC analysis, issue pricing and material variances for cost accounting courses.

27 Material Costing formulas

Material Costing formulas (27)

FormulaExpression
Cost of Materials PurchasedMaterial Cost = Invoice Price + Freight + Insurance + Import Duty + Handling − Trade Discount
Materials ConsumedMaterials Consumed = Opening Stock + Purchases − Closing Stock
Annual Ordering CostAnnual Ordering Cost = (D/Q) × S, D = annual demand, Q = order size, S = cost per order
Annual Holding CostAnnual Holding Cost = (Q/2) × H, H = holding cost per unit per year
EOQ (Holding Cost as % of Price)EOQ = √(2DS/(i × P)), i = holding cost %, P = unit price
Number of Orders per YearN = D/EOQ
Order Cycle (Days)Order Cycle = (EOQ/D) × 365
Economic Production Quantity (EPQ)EPQ = √(2DS/(H(1 − d/p))), d = daily usage, p = daily production rate
Maximum Inventory (EPQ Model)Maximum Inventory = EPQ × (1 − d/p)
Average Inventory (EOQ Model)Average Inventory = Q/2
Reorder Level with Safety StockROL = (Average Daily Usage × Average Lead Time) + Safety Stock
Average Stock Level (Reorder Quantity)Average Stock = Minimum Stock + ½ × Reorder Quantity
Danger LevelDanger Level = Average Daily Consumption × Emergency Lead Time
Total Cost with Quantity DiscountTC = (D/Q)S + (Q/2)H + D × P, P = discounted price
Material Turnover RatioMaterial Turnover = Cost of Materials Consumed/Average Stock
Material Holding Period (Days)Holding Period = 365/Material Turnover Ratio
Simple Average Issue PriceIssue Price = Sum of Prices of Lots in Stock/Number of Lots
Annual Usage Value (ABC Analysis)Usage Value = Annual Units Consumed × Unit Cost
ABC Value ShareValue Share % = (Item Usage Value/Total Usage Value) × 100
Material Wastage PercentageWastage % = (Quantity Wasted/Quantity Input) × 100
Net Material CostNet Material Cost = Gross Material Cost − Scrap Realisable Value
Closing Stock (Stores Ledger)Closing Stock = Opening Stock + Receipts − Issues
Material Price Variance (Purchase Basis)MPV = (Standard Price − Actual Price) × Actual Quantity Purchased
Inventory Carrying Cost RateCarrying Cost % = (Total Carrying Cost/Average Inventory Value) × 100
Lead Time DemandLead Time Demand = Daily Demand × Lead Time (days)
Safety Stock (Service Level)Safety Stock = Z × σ of Lead Time Demand
Reorder Point (Probabilistic)ROP = Lead Time Demand + Safety Stock

About these Material Costing formulas

Material is usually the largest item in the cost of a product, so cost accounting spends a lot of time on how much to order, when to order and how to price what is issued to production. The formulas below cover the order quantity (EOQ and EPQ), the stock levels that trigger an order, and the measures used to monitor stock.

Most problems give annual demand, the cost of placing one order and the cost of holding one unit for a year. Keep all three on the same time basis before you substitute.

How to use these formulas

Worked example

Question. Annual demand is 12,000 units, ordering cost is Rs. 300 per order and holding cost is Rs. 12 per unit per year. Daily usage is 40 units, lead time is 10 days and safety stock is 100 units.

EOQ = √(2DS/H) = √(2 × 12,000 × 300 / 12) = 774.6 units (about 775).

Orders per year = 12,000 / 774.6 = 15.5.

Annual ordering cost = 15.49 × 300 = Rs. 4,648 and annual holding cost = (774.6 / 2) × 12 = Rs. 4,648. They are equal, as expected at the EOQ.

Reorder level = (40 × 10) + 100 = 500 units.

Common mistakes

FAQ

What does the EOQ model assume?

Constant demand, a fixed cost per order, a fixed holding cost per unit, no shortages and immediate delivery of each order. When these do not hold, the EOQ is only a starting point.

What is the difference between EOQ and reorder level?

EOQ says how much to order. The reorder level says when to order, based on usage during the lead time plus any safety stock.

What is ABC analysis?

It ranks stock items by annual usage value (units × unit cost). A small number of items (A) usually account for most of the value and get the tightest control, while many low-value items (C) get simple control.